The Cost Management processes and their associated tools and techniques are usually
selected during which of the following?

  • A. Project finance management
  • B. Project cost estimation
  • C. Project life cycle definition
  • D. Project plan development
Created 8 months, 2 weeks ago by vikaspnra@gmail.com

vikaspnra@gmail.com

Not a correct answer. refer to PMBOK 5th edition , page - 195. The Cost Management processes and their associated tools and techniques are usually selected during Plan cost management, and documented in cost management plan.

jeff212

So what is the answer to this question?

Karolilsk

None from the given options. May be this is one of the trial questions ?

Ahmedelhafid

A

Ahmedelhafid

C

Karansharma

B

vivek7sa

c

kiftekhar

Based on PMBOK pg 554 definition, the closes correct answer is C, this could be a trial question tooo