CSM-001 question 5 discussion

answered

What happens when the Sprint is cancelled?

  • A. The Scrum Team disbands immediately
  • B. The complete Sprint Backlog is put back to the Product Backlog
  • C. The completed Sprint Backlog items are evaluated for a release and incomplete items are discarded
  • D. The completed Sprint Backlog items are evaluated for a release and incomplete items are put back to theProduct Backlog
Created 8 months ago by Santosh.bizanalyst

Santosh.bizanalyst

D. The completed Sprint Backlog items are evaluated for a release and incomplete items are put back to theProduct Backlog

BSS

D. The completed Sprint Backlog items are evaluated for a release and incomplete items are put back to theProduct Backlog

Nilesh293

D. The completed Sprint Backlog items are evaluated for a release and incomplete items are put back to theProduct Backlog

jamosakbs@yahoo.com

D. The completed Sprint Backlog items are evaluated for a release and incomplete items are put back to theProduct Backlog

sdurai

D. The completed Sprint Backlog items are evaluated for a release and incomplete items are put back to theProduct Backlog