PMP question 102 discussion

answered

A project manager seeking insight on previous stakeholder management plans and their
effectiveness should evaluate:

  • A. Historical information and the lessons-learned database.
  • B. Historical information and the stakeholder register.
  • C. Organizational process assets and the lessons-learned database.
  • D. Project documents and historical information.
Created 5 months, 4 weeks ago by irvine15

irvine15

I think B would be a better answer because historical information would be included in the Organization process assets

sharekapmp

C

jfrudd

Okay, historical information is part of the OPA. So A and C are the same. Just that A is a little more specific. If PMP is looking to give perfectly right answers and one is .001% better than the other because it is more precise, that stinks.