PMP question 125 discussion

answered

Which of the following risk response strategies involves allocating ownership of a positive
risk to a third party?

  • A. Mitigate
  • B. Transfer
  • C. Share
  • D. Avoid
Created 5 months, 4 weeks ago by irvine15

irvine15

I believe it should be B. Allocating ownership of a positive risk to a third party is Transfer

Nipun_garg

Transfer would have been correct if its a negative risk.

sharekapmp

Me too thats correct

jayb082

11.5.2.2 Strategies for Positive Risks or Opportunities Share. Sharing a positive risk involves allocating some or all of the ownership of the opportunity to a third party who is best able to capture the opportunity for the benefit of the project. Other options for positive risks include Exploit, Enhance and Accept which are not possible answers here.