There are five inputs to the quantitative risk analysis process. Which one of the following is
NOT an input to the perform quantitative risk analysis process?

  • A. Risk register
  • B. Risk management plan
  • C. Cost management plan
  • D. Enterprise environmental factors
Created 3 months, 2 weeks ago by konrad.piorecki

konrad.piorecki

According to PMBOK5 the Enterprise environmental factors are input to the Perform Quantitative Risk Analysis process, see page 334, figure 11-11 in the PMBOK5